letter to Rudolph Hr.Sascha
Dear Mr. Rudolph, (You A. .........)
again one week has passed .... (No matter, this must only pay for the building owners)
On Friday I called the BL to know how it expected weitergeht.Wir of course it goes with a favorable weather forecast
IMMEDIATELY. In the past, so we set IMMEDIATELY all the work when it looked like bad weather.
We got the info .... Quote Hr.Hochstatter.
-The carpenter has my "Go get it, and it can go.
Then I said.
-Super, which I came out when he will appear for on the site.
Hr.Hochstatter said ....
-I phone today with him and give to you today (16.01.09) or information.
conversation END.
I knew we would get no more info, it seems to pass since the start.
Anyway, we were just happy that it goes on.
At 19:01:09, I wrote an email to the BL, he informed the shell (so that he can get his Ziegelsäge from the floor down)
have no idea why I ever do something like that.
This mail was read receipt! It was not read until today !!!!!!!!.
So, now is the 22.01.09, the whole week was good weather and temperatures in the plus range. Nevertheless
has done nothing.
be honest, we have slowly the snout full.
Who is responsible? The BL-
-German
massive house or the carpenter
We are sorry to take into account the cost of other errors.
We both work at BMW in the logistics, our suppliers komen from all over Germany and Europe.
Every day about 300 trucks are unloaded.
NOT LIKELY DUE TO BAD WEATHER THE WORK SETTING!
In your mail, you describe the situation as if everything in Germany for several weeks resting.
This we do not accept excuses.
Strangely, was in our neighboring site (you know Town & Country) in the last two weeks
the roof is finished completely and installed the windows and doors.
Does the prohibition of the trade association for DM-only sites?
takes to set up, the roof is usually 2 days, it can not be true that no one comes to the site.
It is not our concern whether the craftsman is 10 or 800 miles from Munich.
us, it happens on Monday when bad weather is coming, the rest of the week and no more.
the artisans have chosen. But that should not be to our disadvantage.
Please arrange the work for us on Friday and Saturday , as everywhere else.
If I buy something for 150,000 €, I expect a TOP service.
Until now, the service lousy (architect / construction manager / DM in sonst.MA that make the well-known Telefonspielchen with the bra).
It's unbelievable how we deal with is is.
We chose the DM, because we thought a young company to grow and earn a good name
.
understand why I'm getting a lot Bauforen are full of negative experience with DM.
If there are discrepancies at BMW, is first informed of the process solution makers.
If denied, the issue goes to the group leader, then the department head.
Sometimes even to the plant manager.
latest on this level has solved the problem.
is now our problem is already in the management and unfortunately does nothing at all.
To whom shall we go now?
CAN NOT BE THAT WE PAY FOR SERVICES AND NOT FOR GET. IT MAY BE THE
NCHT THE CARCASS NOW BEEN 6 WEEKS WITHOUT ROOF (2 days work) IS.
MAY NOT BE AS YOU CAN NOT MAKE THE SITE MANAGER GF (we pay) TO MOVE U.S. TO TELL U.S. NOT ALWAYS BE
AND LIES.
If the carpenter's fault, why can not say 'Come at once, or was the last collaboration with DM "
It will surely put pressure on service providers.
Think up what, so we can not work together.
PS: Do you think I have a mind to write such mails constantly?
We could build a house for himself, but wanted to with 2 children we save ourselves the stress, by a reliable property developer
does the work for us selected.
We expect a statement about whether the construction period (5 months, which is signed) must be observed at all.
family Lesar